2007-2010 - JTI Cigarette Factory - Romania

„Turn Key” project (advanced design, hydraulic calculations, execution, commissioning and start-up) for the sprinkler and interior hydrants installation in accordance with FM and Romanian latest rules and regulations:

  1. „Turn Key” project (advanced design, hydraulic calculations, execution, commissioning and start-up) for the sprinkler installation in accordance with FM and Romanian latest rules and regulations for a total area of 13.700 m²:
  • „CRES” area with a total of 1.750 m²;
  • Finite Product Warehouse area with a total of 2.800 m²;
  • „Make & Pack” area with a total of 3.000 m²;
  • „Primary” area with a total of 1.750 m²;
  • „Cut Filler” area with a total of 1.600 m²;
  • Production Offices area with a total of 2.800 m².
  1. „Turn Key” project (advanced design, hydraulic calculations, execution, commissioning and start-up) for the interior hydrants installation in accordance with FM and Romanian latest rules and regulations for a total area of 13.700 m²:
  • „CRES” area with a total of 1.750 m²;
  • Finite Product Warehouse area with a total of 2.800 m²;
  • „Make & Pack” area with a total of 3.000 m²;
  • „Primary” area with a total of 1.750 m²;
  • „Cut Filler” area with a total of 1.600 m²;
  • Production Offices area with a total of 2.800 m².
  1. Tests, service and continuum maintenance for the two Pump Station installation in accordance with FM and Romanian latest rules and regulations.
  1. Tests, service and continuum maintenance for the two water tanks, each with a volume of 1.000 m³, in accordance with FM and Romanian latest rules and regulations.